Toronto Transit Commission Keele Yard Retrofit

The work under Keele Yard Retrofit Contract includes the retrofit of the Keele Yard subway storage facility, includes fire main rehabilitation, sprinkler system and lighting replacement, storm sewer rehabilitation work, south fencing replacement, traction power cabling and provisions for yard security installation.

Project PDF

Client

Toronto Transit Commission
Branko Slovac

Consultant

TTC-Engineering Dept.

Cost

$7,094,795

Completion

December 2016

Location

Toronto, ON

Project Manager

Marco Mancinelli

Site Superintendents

Mike Greenizan